Data Motion question

biescas
1,711 Views

Hi,

I have a technical question about the capability of Data Motion. I need to know, once Data Motion has been put in place – whether the source and destination can be kept in sync on a timed / scheduled basis prior to cutover. Currently it appears that any mirror updates between source and destination need to be manually updated.

Regards,

Elias

1 REPLY 1

scottgelb
1,711 Views

you can edit snapmirror.conf on the target and keep the mirrors running on schedule prior to cutover.  Then the cutover will update snapmirror.conf to semi-sync and all should work.