How to use Snap Creator GUI Scheduler in Cron mode

The GUI scheduler can be used in cron mode which provides more granularity than our standard schedules.

The GUI scheduler is quartz and the documentation can be found here: http://www.quartz-scheduler.org/docs/tutorials/crontrigger.html

An example of a schedule to run monday through friday between 8-17 would be as follows:

0 0 8-17 ? * MON-FRI

One trick is the ? which basically ignores field must be either set for month or day of week so either the 4th or 6th field. Also a minimum of 6th fields is required. The optional 7th field is documented in the above URL.

Regards,

Keith

I did not see any pointer to this documentation in the admin guide of snapcreator 3.4.0

This document was generated from the following discussion: Thread Link : 14443

Please Note:

All content posted on the NetApp Community is publicly searchable and viewable. Participation in the NetApp Community is voluntary.

In accordance with our Code of Conduct and Community Terms of Use, DO NOT post or attach the following:

  • Software files (compressed or uncompressed)
  • Files that require an End User License Agreement (EULA)
  • Confidential information
  • Personal data you do not want publicly available
  • Another’s personally identifiable information (PII)
  • Copyrighted materials without the permission of the copyright owner

Continued non-compliance may result in NetApp Community account restrictions or termination.

Replies

Thanks a lot, Keith. That was easy. I tried it, and it works well.

cron1.jpgcron2.jpg

(This schedule runs @ 8:30,10:30,12:30,14:30,16:30 Mon to Fri)