Is it possible to back up another SG in parallel with SME5.0?

Two or more SG is backed up by one job now, and time hangs very much.

Is it effective though it wants to shorten time by the thing assumed to be one per SG job?

The time of verify is that time hangs, and I think that I am effective to do the sequential lead in parallel.

-masaru

1 REPLY 1

sourav

Hi Masaru,

SME only supports concurrent backup verification but not concurrent backup itself. Please refer the IAG for more details.