we run the Snap Creator for VMware Backups. When the Snap Creator starts two or more jobs at the same time (every day 0:00) some jobs failed with the error:

 

ERROR: SCF-00066: Agent validation failed for [10.79.3.200:9050] with error [Connection refused: connect].

 

but the other jobs run without problems. All jobs use the same agent.

Is it posible that the agent can handle only one job at the same time?

 

Tobi

2 REPLIES 2

Re: Snap Creator two jobs at the same time failed

Jeff_Yao

just try to help..

could you try to separate the jobs into 2-3 batches? like 2-3 jobs every 5 minutes untill all have been submitted?

it might be due to too many jobs at sam time, your agent can't respond back asap.

 

thanks

 

Jeff

Re: Snap Creator two jobs at the same time failed

TobiasKarl

Thank you for your answer.

 

Our Solution is here the update to 4.3.

 

Tobi

View solution in original post