Data Backup and Recovery

Snap Creator two jobs at the same time failed

TobiasKarl
3,416 Views

Hi,

 

we run the Snap Creator for VMware Backups. When the Snap Creator starts two or more jobs at the same time (every day 0:00) some jobs failed with the error:

 

ERROR: SCF-00066: Agent validation failed for [10.79.3.200:9050] with error [Connection refused: connect].

 

but the other jobs run without problems. All jobs use the same agent.

Is it posible that the agent can handle only one job at the same time?

 

Tobi

1 ACCEPTED SOLUTION

TobiasKarl
3,288 Views

Thank you for your answer.

 

Our Solution is here the update to 4.3.

 

Tobi

View solution in original post

2 REPLIES 2

Jeff_Yao
3,325 Views

just try to help..

could you try to separate the jobs into 2-3 batches? like 2-3 jobs every 5 minutes untill all have been submitted?

it might be due to too many jobs at sam time, your agent can't respond back asap.

 

thanks

 

Jeff

TobiasKarl
3,289 Views

Thank you for your answer.

 

Our Solution is here the update to 4.3.

 

Tobi