I want to create the following 3 backup jobs with the following retention plans.
Daily - MTWT - Retain 4
Weekly - F - Retain 4
Monthly - First day fo the month - Retain 1
Is it possible to NOT take the daily or Weekly backup if and when it falls on the monthly schedule?
1 REPLY 1
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
My advice? Let both happen. They'll be tagged differently, and the daily will cycle out after the retention period expires anyway. I would schedule the monthly at a different time than the others to avoid contention.
To answer your question directly, I do not believe there is a way to avoid that scenario. Let me double-check, and if I find out differently, I'll report back!
-Nick