All,

 

We have a snap mirror replication which is in progress and has a throttle. I can change the throttle to get this completed sooner but as far as i know the new throttle parameters will come into effect only for new replication. The one running is a first replication which may be at 50% done and it is over WAN.

 

Is anyway i can accomplist this replication sooner ?

 

Any suggestion is appreciated.

 

Thanks.

1 ACCEPTED SOLUTION

JGPSHNTAP
2,573 Views

If the relationship is throttled, you need to wait until it completes to take the new effect.

 

If you set the global flag, options replication  - than you can jus turn that off

 

I tend to always set global setting, allows for more flexibility

View solution in original post

1 REPLY 1

JGPSHNTAP
2,574 Views

If the relationship is throttled, you need to wait until it completes to take the new effect.

 

If you set the global flag, options replication  - than you can jus turn that off

 

I tend to always set global setting, allows for more flexibility